Wednesday 16 April 2014

Woodham A41 roundabout works - energy from waste plant access

Wednesday 16th April
Work is continuing on the new A41 roundabout at Woodham, with the next phase due to start on 22 April.
The roundabout is part of the ongoing work for the new access road to the energy from waste plant currently under construction at the Calvert landfill site.
Part of the roundabout has already been built to one side of the A41 and the next phase will allow for completion of the roundabout, pavements and bus layby on the northern side of the existing carriageway. To accommodate this work, 24 hour temporary traffic signals will be used at the site from 22 April for a period of 10-15 weeks.
Work is also nearing completion on the Quainton to Edgcott road, where a new bridge deck has been constructed to carry the new access road. It is hoped that the road beneath the bridge will be surfaced next Thursday/Friday (24/25 April) which will allow the road to be re-opened to traffic the following Monday, approximately two weeks ahead of schedule.